Project Scope: Will begin with full abatement followed by demolition.
Estimated Project Cost: $3.6 million/building (State Funding)
Construction Started: Fall 2023 with installation of site fence. First phase of demolition to begin at the end of September (estimated), with the utility disconnection/relocation overlapping.
Update 9/29/23: Furniture removal and abatement crew mobilizing.
Project Scope: The restoration of Byrnes will address the smoke and extinguishing agent that was spread through the building by the mechanical air handling system during the 2018 roof fire. This work must be completed prior to beginning the renovation project.
Project Cost: $4.9 million (Capital Reserve Fund)
Construction Started: Fall 2023
Expected Completion Date: August 2024
Project Scope: Will provide accessibility improvements including an exterior ramp, elevator, restrooms, and seating.
Project Cost: $3.7 million (Capital Reserve Fund)
Construction Started: Fall 2023
Expected Completion Date: August 2024
Project Scope: This first phase of 33 rooms, the work is being completed and is in the system final testing phase. Phase II will commence in the fall. New furniture was also delivered and installed in several classrooms.
Estimated Project Cost: $2.86 million (ICPF)
Installation and Completion Date: Summer 2023
Update 9/29/23: New glass white boards installing in 14 classrooms. Scheduling classrooms for next phase of AV refresh.
Estimated Project Cost: $2 million (Capital Reserve Fund & Aux. Net Position)
Expected Installation and Completion Date: Design and installation is ongoing. Includes new wiring and access points in Kinard.
Additional funds will be employed to upgrade Roddey. Work continues on Kinard, Margaret Nance and Thomson.
Project Scope: Improve accessibility and modernize dated facilities on all floors of the building.
Project Cost: $1.1 million
Construction Started: Summer 2023
Expected Completion Date: Fall 2023.
Update 9/22/23: Bathroom plumbing rough-in nearly complete. Drywall ready to hang.
Project Scope: Fundraising efforts currently underway will replace the existing fountain. Click here for additional information about the history of the fountain and the proposed replacement design.
Project Cost: $500,000 (gift)
Construction Started: Summer 2023
Expected Completion Date: Fall 2023
Update 9/29/23: Concrete base poured. Paver placement to start in about two weeks. Grading and removal of excess soil.
Project Scope: Winthrop funded refreshing most residence hall lobbies, including Margaret Nance, Lee Wicker, Phelps and Thomson, with new flooring, new furniture, lighting, and painting.
Other residence hall-related work has included new furniture in West Thomson, repainted stairwells in Lee Wicker, and new flooring in several Courtyard hallways.
Project Scope: Project involved removing pergolas and installing group seating options.
Project Cost: $50,000 (ICPF Funds)
Construction Started: May 2023
Completed: August 2023
Project Scope: This project will address accessibility campus wide and improvements will be ongoing.
Estimated Project Cost: $50,000 per phase
Accessible Route Upgrades Phase II Expected completion: August 2023
Accessible Route Upgrades Phase I Completed: September 2022
Project Scope: Overall beautifying of campus buildings
On-going
Project Scope: Both sides of this major thoroughfare will soon convey a more consistent and welcoming look.
Construction Started: September 2023
Update 9/29/23: Removal finished from Cherry Road to Eden Terrace. Next section to start will be Eden Terrace to Myrtle Drive.
West Center and Dacus Library roof replacements ongoing
September 1, 2023 Project Update (PDF - 3.9 MB)
June 1, 2023 Project Update (PDF - 3.5 MB)
Project Scope: Will replace the university’s main substation of its 50-year-old electric distribution system.
Project Cost: $2 million (EDA Grant & Capital Reserve Fund)
Expected Construction Starting Date: Fall 2023
Expected Completion Date: January 2024
Estimated Project Cost: $1.2 million (Capital Reserve Fund)
Expected Project Starting Date: Spring 2023
Expected Completion Date: August 2024
Project Cost: $560,000 (Capital Reserve Fund)
Expected Completion Date: Fall 2023
Project Cost: $250,000 (Capital Reserve Fund)
Expected Completion Date: Fall 2023
Project Cost: $250,000 (Capital Reserve Fund)
Expected Completion Date: December 2023
Project Cost: $250,000 (Capital Reserve Fund)
Expected Completion Date: Fall 2023
Estimated Project Cost: $1 million (Capital Reserve Fund)
Expected Construction Starting Date: Fall 2023
Expected Completion Date: Spring 2024
Estimated Project Cost: $1.2 million (Capital Reserve Fund)
Expected Construction Starting Date: Summer 2023
Expected Completion: Spring 2024
Estimated Project Cost: $4.1 million (Capital Reserve Fund)
Expected Construction Starting Date: Fall 2023
TBD
TBD
Estimated Project Cost: $2.7 million (Aux. Net Position)
Expected Construction Starting Date: Spring 2024
Project Scope: Replace select aging fan coil HVAC units.
Expected Construction Starting Date: Fall 2023
Expected Completion: Early 2024
Project Scope: Sound system repairs, new LED lights for seating, court lighting.
State-funded.
Work Started: Summer 2023
The Comprehensive Permanent Improvement Plan (CPIP) is a tool that informs decision-makers of the anticipated permanent improvement projects an agency plans to initiate over a five-year period. It promotes awareness of funding needs for permanent improvement projects and informs the Joint Bond Review Committee and State Fiscal Accountability Authority of the projects that will be forthcoming through the approval processes.
2020 Comprehensive Permanent Improvement Plan (For plan years 2020-2024; see pages 1121-1145)
E&G Deferred Maintenance Master Plan 2019-2030
Auxiliary Deferred Maintenance Master Plan 2019-2030
Project Overview: Project replaced the tile at the plaza between the West Center and Campus Center as well as tile plaza overlooking the Campus Green.
Project Cost: $480,000 (ICPF Funds)
COMPLETED December 2022
Project Cost: $2 million (Capital Reserve Funds)
COMPLETED December 2022
Project Cost: $50,000 (ICPF Funds)
COMPLETED December 2022