Update 11/11/26: About 25% through the deep aggregate piers. Should finish near the end of November. Start foundation/first floor concrete slab mid-November; to finish late December. Office of State Engineer and peer review of construction drawings underway. Precast walls to start Jan. 4.
The first new construction since 2010, a new four-story, 400-bed building will be built along Cherry Road near the site where two former high-rise residence halls—Wofford and Richardson—were demolished in 2024. The approximately 100,000-square-foot project will help meet the university’s surging demand for housing driven by climbing enrollment and a growing slate of new degree programs. Vertical construction is set to begin in January 2027, with interior work commencing in February. Final inspections are targeted for November 2027 to keep the project on track for a spring 2028 opening.
Update 11/11/26: Wrapping up mechanical ductwork. Electrical in wall wiring and devices. Painted drywall. Priming drywall. Upcoming: set ceiling grid, lights, and sprinkler heads.
In the Bookstore: Completed accent painting. Removed old sales counter and installed new one. Setting new pick-up window counters. Starting new entry wall.
Update 11/11/26: Install new storefront window-door system. Installed ceiling tiles.
Update 11/11/26: Dealing with material long lead time on the piping. Working to change piping material so see if we can start sooner. Material lead time will determine start date.
Update 11/11/26: Applying new court coating system. Reinsalling chain link fencing.
Update 11/11/26: Started demolition of old brick risers. To be followed by grading and formwork.
Update 10/19/26: Wrapping up rear dormers. Pricing for front dormers.
Update 10/19/26: New autoclave electrical feed installed in Dalton. New LED stage lights installed in Byrnes. Issued PO for tower masonry waterproofing for Withers and Baseball stadium water proofing, concrete, and steel repairs. Processing POs for Coliseum study room refresh. PO issued for Byrnes AHU 1 motor controller replacement. POs created for Johnson AHU4 fanwall replacement and Tillman Auditorium AHU fanwall replacement. Landscaping for Southwest Gateway and Joynes plaza.
June 2026 Project Update (PDF - 4 MB)
June 2025 Project Update (PDF - 5.27 MB)
January 2025 Project Update (PDF - 4.62 MB)
September 2024 Project Update (PDF - 3.5 MB)
June 2024 Project Update (PDF - 5MB)
January 2024 Project Update (PDF - 1.5 MB)
September 1, 2023 Project Update (PDF - 3.9 MB)
June 1, 2023 Project Update (PDF - 3.5 MB)
Update 10/19/26: SCDOT working design and coordinating alignment with new Residence Hall. Expect to advertise late spring-early summer 2027. Reviewing preliminary design documents.
Update 10/19/26: Finalizing programming concept layout for one-stop shop.
Reviewing possible project funding. Estimated cost: $4.62 million from state capital
reserve budget.
Update 10/19/26: Test fitting feasibility study and Archives space needs with existing floor plan.
Working through SD level pricing. SD pricing for compact shelving. CM-R selected.
Routing contract for signature shortly. Scheduling kick-off call.
High level estimated completion August 2027.
Update 10/19/26: Completed building envelope investigation. PO issued for WiFi equipment.
Update 11/11/26: Removed existing lockers. Construction to start Nov. 23.
Estimated Project Cost: $4.1 million (Capital Reserve Fund)
The Comprehensive Permanent Improvement Plan (CPIP) is a tool that informs decision-makers of the anticipated permanent improvement projects an agency plans to initiate over a five-year period. It promotes awareness of funding needs for permanent improvement projects and informs the Joint Bond Review Committee and State Fiscal Accountability Authority of the projects that will be forthcoming through the approval processes.
2020 Comprehensive Permanent Improvement Plan (For plan years 2020-2024; see pages 1121-1145)