Update 9/18/26: Received state building permit and city site zoning approval and submitted for SCDES. Submitted for stormwater-land disturbance permit. This month, will install site fence and windscreen. Also hope SCDES permit will allow installation of silt fence and inspection. October work: plan to start site utilities and deep pier foundations.
The first new construction since 2010, a new four-story, 400-bed building will be built along Cherry Road near the site where two former high-rise residence halls—Wofford and Richardson—were demolished in 2024. The approximately 100,000-square-foot project will help meet the university’s surging demand for housing driven by climbing enrollment and a growing slate of new degree programs. Vertical construction is set to begin in January 2027, with interior work commencing in February. Final inspections are targeted for November 2027 to keep the project on track for a spring 2028 opening.
Update 9/18/26: New walls framed, rough in electrical and data. Relocated sprinkler heads. Will start
hanging drywall. Finalizing furniture quote. New Career Closet rendering:
finalizing layout, material, and pricing. In the Bookstore portion: framing new walls
and rough in electrical-data for new pick-up location in the rear of store. Core drill
for power-data for new sale counter location coming soon. Will start hanging drywall,
reviewing new graphic packages, and coordinating project scope with the Career Services
renovation.
Update 8/31/26: Markley's (renovate and rebrand old Einsteins and add a salad bar in Markley's). Wrapped up construction. Finishing punch list. On Thomson cafeteria refresh: wrapped up construction and finishing punch list.
Update 8/31/26: Refresh 18 3rd-floor rooms and one 1st-floor room. Punch list items being worked. Furniture move back next Wednesday. Reviewing signage and shop drawings. Planning scope for winter break work.
Update 9/4/26: Final completion and clean-up. Planning additional plants and temporary fence panels to infill gaps.
Update 9/18/26: New fence to be installed this month. Planning new landscaping along Alumni Drive.
Update 9/4/26: Finished priming and painting the fiberglass and wood trim.
Update 9/18/26: Demolition complete. Installing new rough-in electrical and data. Will hang drywall
following electrical inspection. Estimated completion in November, with move-in and
equipment set-up in December. Finalizing design of motion capture system and AV data.
Update 8/31/26: Old basement level flooring abated. Walls and doors trim being primed and painted.
New roller shades installed in select spaces. New flooring to be installed next week.
New room signage installed. Punch list items are being completed.
Update 9/18/26: Started new board installation but need to modify the mounting brackets.
Update 9/18/26: Working procurement paperwork toward award and contract signing. Contractor mobilize
right after disc golf (Oct. 8-11, 2026)
Estimated completion before collegiate disc golf (April 2027)
Contract work duration 120 days
Update 8/31/26: Donor-funded classroom renovation: new paint and carpet, new furniture, new AV. Finishing punch list items.
June 2026 Project Update (PDF - 4 MB)
June 2025 Project Update (PDF - 5.27 MB)
January 2025 Project Update (PDF - 4.62 MB)
September 2024 Project Update (PDF - 3.5 MB)
June 2024 Project Update (PDF - 5MB)
January 2024 Project Update (PDF - 1.5 MB)
September 1, 2023 Project Update (PDF - 3.9 MB)
June 1, 2023 Project Update (PDF - 3.5 MB)
Update 8/25/25: 3D scanning ongoing, historic preservations specialist touring the building.
Update 9/18/26: Contractor to mobilize Sept. 21.
Update 9/18/26: Reviewing pricing.
Update 12/8/25: Started the selection for the CM-R qualifications due Dec. 8.
Update 8/31/26: Renovate locker room new flooring, lockers, and lighting.
Issuing PO. Start November 23 with completion December 31.
Estimated Project Cost: $4.1 million (Capital Reserve Fund)
The Comprehensive Permanent Improvement Plan (CPIP) is a tool that informs decision-makers of the anticipated permanent improvement projects an agency plans to initiate over a five-year period. It promotes awareness of funding needs for permanent improvement projects and informs the Joint Bond Review Committee and State Fiscal Accountability Authority of the projects that will be forthcoming through the approval processes.
2020 Comprehensive Permanent Improvement Plan (For plan years 2020-2024; see pages 1121-1145)